A graphical interface for resource constrained scheduling
Loading...
Date
1992
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
University of New Brunswick
Abstract
This report discusses the development of a graphical interface for resource constrained
scheduling. Some programs, such as Primavera, do level resources but these are black
boxes. The user inputs the required data, the computer performs the calculations and gives
the output. The problem is that the user can not see the calculations that the computer is
performing, therefore it is difficult for the user to intelligently modify the output. This
process is known as a black box.
The interface developed in this report, called RCS(Resource Constrained Scheduling),
displays for the user the resource constrained and squence constrained activities. The
program allows the user to modify the output to find an optimum schedule. The menu
options guide the user through the modification process. Another feature of RCS is that it
allows for interruptions in activities as oppose to delaying the entire activity.